Logo TENAX
View the Site Map of TENAX Worldwide web siteSearch the TENAX web site
TENAX local web sites TENAX Worldwide web site
Geosynthetics
HOME PAGE   PRODUCTS CASE HISTORIES ASSISTANCE EMAIL
Embankment for rock fall protection:
The experimentation   BACK
 

INTRODUCTION
The study of the behaviour of reinforced embankments for rock fall protection, resulted not to be adequately explored. Particularly, the topic of those structures’ behaviour, subjected to the impact of single elements having high impact energyand generally with velocity from “very rapid” to “extremely rapid”, that is from 0.3 m/min to over 30 m/sec, shouldbe faced.
The modern modelling systems of the velocity of the boulders downhill allow to estimate with remarkable precision the height of the protection structure and most of all the location in term of distance of the detachment point along the main unloading directions.
As far as wire netting rock protection barriers are concerned, the state-of-the-art, allowed a resistance capacity up to a total energy over 3000 kJ, indicatively the energy of a boulder of 3 m3 which moves at the speed of about 30 m/sec (100 km/h).
Most of the experts consider the reinforced embankments as a structure which can be set in a range of higher absorption energy compared to the wire netting rock barriers currently on the market. Thus the 2500-3000 kJ threshold seemed to be widely exceeded and, in 1999, in collaboration with Politecnico di Torino, TENAX carried out some full-scale tests. The full-scale tests allowed a quantitative evaluation of the above mentioned mechanisms as well as the development of mathematical models to estimate the behaviour of a given reinforced embankment subject to a fixed impact, providing a realistic design aid for such structures. Checking the behaviour of the reinforced embankments for rock fall protection when high energy impacts occur, provides to government Boards and designers a valid solution in all those cases that cannot be dealt with traditional methods.

 
Description and test procedures
The testing facility where the reinforced embankment for rock fall protection has been tested was located in a valley where a cableway system enabled cubic boulders (l=1.55 m. ca. weighting W=5.000 Kg, and l=1.50 m, weighting W=8.800 Kg) to run in semi-free falling for about 50m.
A release device allowed the boulder to hit the embankment wall at a velocity of 30 m/s with an impact energy of 2500 kJ and 4500 kJ respectively.
The impact phases were recorded through a system of three video cameras with a time code display and a 25 photograms/s taking speed.
The choice of constructing a steep isosceles earth wall leads to a reduction of the soil mass that will oppose the impact. The consequent reduction of the energy absorption capacity is already compensated by the reinforcement provided by geogrids. The filling soil, found on the site, is made up of weathered limestone material with grain size distribution of gravel and of sand with the presence of silts and clays.
 

View of the testing facility and embankment
View of the testing facility and embankment

Testing coordinator:
Prof. Sebastiano Pelizza
(Politecnico di Torino, territory’s Georesources)
Operators: Eng. Daniele Peila, Eng. Claudio Oggeri

Test results
The embankment was not pierced by the boulder which fell at the bottom of the ground wall.

The scheme shows the position of the impact which occurred only in correspondence of the fifth and sixth portion of the wall producing the soil detachment practically only in these portions.
  Section of the testing field
    Section of the testing field
Embankment cross-section
Embankment cross-section

Rock block   TEST 1   TEST 2
 
Rock block mass: 5000 kg
Lext: 1,25 m
V = 30 m/s

The kinetic energy of the block before impact coming from the measurement of the velocity (analysing the photograms of the film taken) is about 2511 kJ.
 
Rock block mass:
8800 kg
Lext: 1,
50 m
V = 30 m/s

The kinetic energy of the block before impact coming from the measurement of the velocity (analysing the photograms of the film taken) is about 4530 kJ.

Falling block   Embankment after impact   Embankment scheme after impact

Falling block

 

Embankment after impact

  Embankment scheme after impact: A - Max depth 67.5 cm
B - Max backside deformation 17.5 cm
    BACK
TENAX International B.V. • Geosynthetics Division
Via Ferruccio Pelli, 14 CH-6900 Lugano, Switzerland • Tel +41+91.9242485 • Fax +41+91.9242489

geo@tenax.net

TENAX SpA - Geosynthetics Technical Office (GTO)
Viale Monza, 1- 20125 Milano (MI), Italy • Tel. +39 02.26113532 • Fax +39 02.28971107

gto@tenax.net

TENAX SpA • Divisione Geosintetici
Via dell'Industria, 3 • I-23897 Viganò (LC), Italia • Tel +39 039.9219307 • Fax +39 039.9219200

geo@tenax.net

© TENAX Group all rights reserved